By submitting this form you agree that Hydroseeding VA may share the details you provide with one or more independent local contractors, and that they and we may contact you by phone, text or email about your enquiry — including by automated dialling or prerecorded message. Consent is not a condition of any purchase and you can withdraw it at any time by replying STOP or telling the caller. Message and data rates may apply. See our privacy policy and terms.
Silt fence works by slowing runoff enough that suspended soil drops out before the water leaves the site. That is the whole mechanism, and it explains both why it is required and why it disappoints people.
It settles sand and coarse silt well. It does very little about clay-sized fines — and on the Piedmont side of the metro, fines are exactly what you are producing. Those particles stay suspended long past the time the water spends behind your fence, which is why the runoff leaving a clay site still looks like coffee.
So treat it as the legally required starting point, not as the plan. On clay the things that actually reduce sediment are getting cover established fast, blankets and matting on slopes, and controlling where the water goes in the first place.
Four mistakes account for nearly all of it.
The bottom of the fabric has to go into a trench and be backfilled and compacted. Fence stapled to stakes and left sitting on the surface just lets the water run underneath, which is the most common failure on residential sites by a wide margin.
Silt fence works along the contour. A run angled downhill concentrates flow at the low point and blows the fence out there. J-hooks at the ends turn the flow back on itself.
Once sediment reaches roughly a third of the fence height it stops working. Nobody comes back to clean it, and then everyone is surprised when it overtops.
Silt fence is not a check dam and it is not a diversion. Concentrated flow needs a rock check, a diversion or a sediment trap. Fabric across a channel will fail, every time.
Most localities describe the escalation vaguely. Hanover states it outright: under an acre, if the site can be controlled with silt fence plus a gravel construction entrance, you are on the simple track. Need more than that and you are into an engineered erosion and sediment control plan with a bond behind it.
That is a useful test everywhere in the metro, whatever your county calls it. If your site needs diversions, traps or check dams, stop treating it as a fencing job.
No surprises in the middle.
We look at where the water currently goes, not just the boundary. The right fence line follows the contour, which is rarely the property line.
If you have an approved plan we install to it. If you do not have one yet, we will tell you whether you need one.
Fabric into a trench, stakes on the downhill side, backfilled and compacted. This is the step that gets skipped.
It either passes or it does not, and the difference is almost always the trench.
Cleaned out as sediment builds, and removed once the site is stabilised — which in Richmond city means once your cover is established enough to release the surety.
If your disturbance crosses your locality’s threshold, you need sediment control and silt fence is usually part of it. In Richmond city that threshold is 4,000 square feet, or 2,500 inside a Chesapeake Bay Preservation Area. Those are ordinary residential numbers.
It is priced by linear foot and the number moves with access, ground conditions and whether the run needs trenching through rock or roots. We would rather walk it than publish a rate that turns out to be wrong on your site.
Legally, on your own property, usually yes. Practically, the trench is the whole job and it is harder than it looks in clay. If it fails inspection you pay twice.
Until the site is stabilised. On a Richmond city job that is tied to the surety release at 75 percent living perennial vegetation, so the fence and the seeding are on the same timeline whether you planned it that way or not.
Partly, and less than you would hope. It catches the coarse fraction. Clay fines stay suspended and pass through. That is not a reason to skip it — it is required — it is a reason not to rely on it alone.
Tell us the site, the size and roughly when. We’ll come back with a local price.
Tell us what the site needs and roughly how big it is. We’ll match you with a crew that works your county and get you a written price.
Tell us where the job is and we’ll get you a local quote.
By submitting this form you agree that Hydroseeding VA may share the details you provide with one or more independent local contractors, and that they and we may contact you by phone, text or email about your enquiry — including by automated dialling or prerecorded message. Consent is not a condition of any purchase and you can withdraw it at any time by replying STOP or telling the caller. Message and data rates may apply. See our privacy policy and terms.